Activities | Total duration (number of weeks) | M1 | M2 | M3 | M4 | M5 | M6 | M7 | M8 | M9 | M10 | M11 | M12 | ||
Work package |
Ref.nr/ Sub-refnr |
Title | |||||||||||||
WP 1 | 1.1. | Analysis of EU master study programmes in the field of DBBT | 5 | X= | 2= | 2= | 2= | ||||||||
1.2. | Analysis of WB master study programmes in the field of ICT | 5 | X= | 2X | 2X | 2X | |||||||||
1.3. | Comparative analysis of study programmes in the fields of DBBT from EU and ICT from WB | 3 | X= | 2X2= | |||||||||||
1.4. | Study Visits to EU partner HEIs | 4 | 2= | 2= | |||||||||||
1.5. | Consulting with the partners from the business | 1 | X | X | X | ||||||||||
1.6. | Teachers training | 4 | X= | X= | X= | X= | |||||||||
WP 2 | 2.1. | Purchase of hardware equipment | 4 | X= | 2X | X | 4X | ||||||||
2.2. | Purchase of software | 3 | X= | X | X | 4X | |||||||||
2.3. | Purchase of literature | 0 | |||||||||||||
2.4. | Training the staff for use of equipment | 2 | 3X | ||||||||||||
2.5. | Set up of DBBT laboratory | 4 | 4X | 4X | |||||||||||
2.6. | Design of teaching materials | 1 | X= | ||||||||||||
2.7. | Methodological instructions for teaching | 2 | X= | X= | |||||||||||
2.8. | Methodological instructions for students’ practice | 2 | X= | X= | |||||||||||
WP 3 | 3.1. | Defining the principles and model for academic master studies in the field of DBBT | 4 | 2X= | 2X= | ||||||||||
3.2. | Defining the teachers' competencies and learning outcomes of courses for academic master studies in the field of DBBT | 4 | 2X= | 2X= | |||||||||||
3.3. | Design of new curriculum for academic master studies in the field of DBBT | 10 | 2X2= | 4X | 2X2= | 2X2= | 2X | ||||||||
3.4. | Printing the book of curriculum for academic master studies in the field of DBBT | 2 | 2X | 3X | |||||||||||
WP 4 | 4.1. | Defining the principles and model for vocational master studies in the field of DBBT | 2 | X= | X= | ||||||||||
4.2. | Defining the teachers' competencies and learning outcomes of courses for vocational master studies in the field of DBBT | 2 | X= | X= | |||||||||||
4.3. | Design of new curriculum for vocational master studies in the field of DBBT | 6 | 2X2= | 2X | X= | 2X2= | 2X | ||||||||
4.4. | Printing the book of curriculum for vocational master studies in the field of DBBT | 2 | 2X | 2X | |||||||||||
WP 5 | 5.1. | Enrollment of students to academic master studies | 0 | ||||||||||||
5.2. | Enrollment of students to vocational master studies | 0 | |||||||||||||
5.3. | Implementation of academic and vocational master study programmes | 0 | |||||||||||||
5.4. | Monitoring the first generation of students on new study programmes | 0 | |||||||||||||
5.5. | Analysis of the students' feedback | 0 | |||||||||||||
5.6. | Students' practice with business partners | 0 | |||||||||||||
5.7. | Lectures by experts from business | 0 | |||||||||||||
WP 6 | 6.1. | Regular Quality Board meetings | 2 | X= | X= | X= | |||||||||
6.2. | Development of the Quality Control plan | 2 | 2X= | ||||||||||||
6.3. | External financial control | 0 | |||||||||||||
6.4. | Internal evaluation of the project | 1 | X | ||||||||||||
WP 7 | 7.1. | Promotion on internal meetings in partner institutions | 1 | X | X | X | |||||||||
7.2. | Promotion on Website & social networks | 9 | 2X | 2X | 2X | 2X | 2X | 2X | 2X | 2X | 2X | 2X | 2X | 2X | |
7.3. | Production of promotional material | 1 | X= | ||||||||||||
7.4. | Promotion in WB HEIs | 0 | |||||||||||||
WP 8 | 8.1. | Accreditation of new academic and vocational master study programmes | 0 | ||||||||||||
8.2. | Creation of academic sustainability plan | 0 | |||||||||||||
8.3. | Creation of financial sustainability plan | 0 | |||||||||||||
8.4. | Signing the long-term cooperation agreements between HEIs and all relevant stakeholders | 1 | 2X | ||||||||||||
8.5. | Ensuring the support of the relevant government bodies | 1 | 2X | ||||||||||||
WP 9 | 9.1. | Regular Steering Committee meetings | 3 | 2X | X= | X= | |||||||||
9.2. | Regular Project Management Committee meetings | 0 | |||||||||||||
9.3. | Development of guidelines on the project management and reporting | 3 | 2X= | 2X= | X= | ||||||||||
9.4. | Day-to-Day coordination activities | 12 | X= | X= | X= | X= | X= | X= | X= | X= | X= | X= | X= | X= | |
9.5. | Producing the project Interim Report | 0 | |||||||||||||
9.6. | Producing the project Final Report | 0 |